Case study
Type:
Farm Turbine
Status:
Operational
Owner:
Foresight
Pitts Down Farm turbine is built on agricultural land adjacent to the B2287, around 3km to the east of Tregony in Cornwall. The project comprises a single EWT DW54 turbine and has generating capacity of 500kW.
A planning application for the project was submitted to Cornwall Council in December 2013 and consent was granted in September 2014.
The project was accredited for the then Feed-In Tariff scheme in September 2015 and acquired by AGR in xxx 2016. Construction immediately followed and commercial operations began in July 2016. The project was acquired by Foresight from AGR in yyy [Toby/Trev - can you figure out the details?]
Toby/Trev? We'll need to change the title to something other than Community and figure out something else to write about here... Same will also apply to Pitts Down, Orrell and Bellevue. Though I see there was supposed to be a community benefit fund of £5k/MW/yr...
50° 17′ 03″ North, 4° 52′ 18″ West
What is being delivered