Since 2007, we’ve worked in partnership with landowners and communities to develop the projects needed to repower the UK with clean electricity
21
Projects
We have to date completed 7 projects and a further 14 (in the public domain) are now in different stages of development.
1.2m
Homes powered
The operational projects we’ve developed are already generating clean electricity for over 90,000 homes. Those in development will power over 930,000 more.
200
Years of Team Experience
Our team has more than 200 years’ collective experience in renewable energy development work - 120 of those gained within Coriolis Energy itself.
1,400 MW
Capacity
The combined capacity of the operational projects we have developed stands at 125 MW. Those in development will have a capacity of 1,300 MW.
£1.6bn
Capital investment
Over £150 million has already been invested in constructing the operational projects we’ve developed. A further £1.5 billion set to be invested in delivering those currently in development.
100
Landowners
We’ve completed agreements with over 100 landowners to host project infrastructure or provide access - each of whom now receives an income from a clean energy project.
Partnering with landowners To bring projects to life
Clean energy projects are a great way to diversify income in an increasingly challenging rural economy.
We work in close partnership with landowners from the outset to unlock the full potential of their land, ensuring each project complements existing land uses and delivers long term economic benefits.
Community benefit funds have been established for our operational wind farms, and similar schemes will be set up for those now in development. These support a range local initiatives - from community facilities and education programmes to environmental projects.
We also offer opportunities for commuinity investment and prioritise local suppliers during construction and operation, ensuring our projects deliver benefits beyond clean energy.
Committed to sustainability For the good of the planet
Sustainability guides everything we do - from site selection all the way through the design process. We assess environmental, social, and economic impacts, working with independent experts to protect habitats, cut carbon emissions, and respect local landscapes. Our aim is to create clean energy projects with a lasting environmental legacy.
Potential new sites are carefully screened for environmental suitability, wind resource and proximity to the grid. For those that meet these criteria, commercial terms are agreed with the landowners and projects then move forward into development.
Development
Detailed environmental surveys are undertaken, often over several years, to inform designs and avoid unacceptable impacts. Local communities are consulted, planning applications submitted, and connection agreements negotiated with the network operators.
Construction
Following planning approval, electricity sales contracts are negotiated and the project moves into construction. This typically takes 12–24 months, with local contractors used where possible. A community liaison group keeps residents informed throughout.
Operation
Once operational, a project generates clean power for 30–40 years. Very little ongoing maintenance is needed and availability levels are typically over 97%. Part of the income generated is used to support a local community fund.
Decommissioning
At the end of a project’s life the wind turbines and other equipment are removed from site and the foundations broken down to a depth of at least a metre. The land is then restored or a fresh planning application submitted to develop a new project.
Site assessment
Potential new sites are carefully screened for environmental suitability, wind resource and proximity to the grid. For those that meet these criteria, commercial terms are agreed with the landowners and projects then move forward into development.
Development
Detailed environmental surveys are undertaken, often over several years, to inform designs and avoid unacceptable impacts. Local communities are consulted, planning applications submitted, and connection agreements negotiated with the network operators.
Construction
Following planning approval, electricity sales contracts are negotiated and the project moves into construction. This typically takes 12–24 months, with local contractors used where possible. A community liaison group keeps residents informed throughout.
Operation
Once operational, a project generates clean power for 30–40 years. Very little ongoing maintenance is needed and availability levels are typically over 97%. Part of the income generated is used to support a local community fund.
Decommissioning
At the end of a project’s life the wind turbines and other equipment are removed from site and the foundations broken down to a depth of at least a metre. The land is then restored or a fresh planning application submitted to develop a new project.
Is my land suitable? Try our site assessment tool to find out